Forrestania Resources puts finishing touches on December WA gold restart

Writer: Murray Ward
Murray Ward
6 hours ago
3 min read
Forrestania puts finishing touches on December WA gold restart
A run-of-mine (ROM) loader at Forrestania Resources’ Edna May gold mine loads ore onto the ROM pad ahead of first production in December. Credit: File

 

 

Forrestania Resources (ASX: FRS) has ticked a string of key operational boxes as it barrels towards a December first gold pour at its Edna May Gold mine in Western Australia, locking in critical supply and services contracts and establishing a new operational hub in the heart of the Goldfields.

 

In a significant step towards wet commissioning, Forrestania has executed a long-term supply agreement with Australian Gold Reagents for sodium cyanide, a critical reagent required for gold recovery operations.

 

At the same time, the company has awarded the ore loading and crusher feed contract to Campbell Gold Haulage. The deal supports ore handling requirements at both its 2.9-million-tonne per annum (Mtpa) Edna May and 3.2Mtpa Lake Johnston hubs. It also delivers operational efficiencies, as Campbell already holds the road train contract for delivering ore to both of Forrestania’s run-of-mine (ROM) pads. Campbell has already begun mobilising equipment and personnel to site.

 

To support its growing operational footprint, Forrestania has now planted a flag in Kalgoorlie, establishing a dedicated office that will serve as its goldfields operations hub. The company says the new facility showcases its commitment to building a long-term operating presence in WA's premier gold district. In a savvy operational move, the new office will be shared with Forrestania's mining contractor MEGA Resources.

 

The office will be led by newly appointed "general manager mining", Darren Gaby, an experienced hand with more than three decades of operational and project development experience in the WA goldfields. Notably, Gaby previously led the development of Beacon Minerals’ Jaurdi Gold project from construction through to production.

 

Forrestania says it has 60,000 tonnes of ore on the ROM pad at Edna May, with first processing fast approaching. Its second strategic hub at Lake Johnston, slated to be operational in early 2027, is also well-stocked, with ore inventories exceeding 180,000 tonnes and the ROM stockpile near full capacity.

 

The company says the supply and haulage agreements are key to the transition from dry to wet commissioning, with its first gold pour at Edna May targeted for December this year.

 

These initiatives represent important milestones in the systematic build-out of Forrestania's operating platform as we progress toward production at Edna May. With approximately 60,000 tonnes of ore available on the ROM stockpile, and first ore processing at Edna May fast approaching, alongside ore inventories of over 180,000 tonnes and continuing to build at Lake Johnston with the ROM stockpile near full capacity, our focus is on ensuring every element of each operation is in place for a successful transition to production.   Forrestania Resources Executive Chairman

 

Forrestania’s hub-and-spoke growth strategy is centred on its Edna May and Lake Johnston plants, initially processing ore from its own deposits. However, the company is also aggressively building an inventory of additional ore sources via a raft of recent ore-purchase agreements from local miners, all within economic haulage distance of its hungry, soon-to-be operational, processing infrastructure.

 

The company's regional consolidation strategy gained another boost recently after completing its takeover of Zenith Minerals. The company now holds a 72.56 per cent controlling interest in Zenith, adding a further 675,000 inferred ounces of gold to its burgeoning resource base.

 

Forrestania's light-speed progress comes as the WA gold sector continues to fire on all cylinders, with exploration expenditure in the State hitting a record A$1.57 billion and production forecast to climb in the coming years. Recent high-value transactions such as Genesis Minerals’ $5.6 billion bid for Vault Minerals and OceanaGold’s $776 million bid for Ausgold have also highlighted the renewed appetite for regional gold assets and processing infrastructure, putting a spotlight on developers with a clear path to production.

 

With key contracts now signed, ore stacked up on the pad and a seasoned operator at the helm in Kalgoorlie, Forrestania appears to be getting its ducks in a row ahead of the crucial transition from developer to producer. As the company rounds the final corner toward its first gold pour, the market will likely watch closely as it vies to join the ranks of WA’s gold miners.